Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

Work to start on Staplefield Wetlands

By Sarah Abellan, Clerk Ansty and Staplefield Parish Council

Wednesday, 19 February 2025

ABOUT THE AUTHOR

Ansty and Staplefield Parish Council Contributor

VIEW ALL ARTICLES BY THIS AUTHOR

Letter being sent out to around 130 houses in Staplefield later this week by Southern Water regarding the Wetlands being created at Cuckfield Road, Staplefield, West Sussex RH17 6ES.

Hello,
We’re creating a new wetland at Staplefield
As you know last year, we received planning permission to create a wetland on land to the should of Staplefield village. The new wetland once up and running will help reduce phosphate levels before the water enters the river.
What happens next?
We’re starting work on 3 March where we will begin by setting up our site offices and welfare facilities. We expect this work to take around four weeks to complete following which, in early April will start constructing the wetland.
How will this affect you?
• During this time, we’ll be constructing the access road from field entrance around perimeter of field towards compound (see map)
• We’ll establish and set up the site compound
• Erect site fencing
• Take delivery of welfare cabins and connect up temporary services
• Take delivery of materials and plant which will be used in the creation of the wetland
We expect to have the wetland construction and internal site upgrade work to be completed by September this year. Our working hours will generally be 7.30am – 5.30pm. We do not plan to work weekends but if we had to, we’d let you know beforehand.

How to contact us
Please contact Matthew Thompson, Communication and Communities Lead, GTb, on 07810 655423 or thompsonm@binnies.com, Monday to Friday, 9am to 5pm.
Alternatively, please call Southern Water, out of hours, on 0330 3030 368. Just tell us you’re calling about Capital Projects, with Project Reference Number (PRN) 752214, so we can help you more quickly. Or you can email us at capitalcomms@southernwater.co.uk
We would like to thank you for your support and patience whilst we undertake this essential work.